Eldorado Reports 2015 Year-End and Fourth Quarter Financial and Operational Results

In the annual review of  Eldorado Gold, ( read the full review here) there is a detailed report on the progress of the company’s investments in Greece , as follows :

 GREECE

In order to complete the construction and development of its Kassandra mining projects in Halkidiki, northern Greece, Hellas Gold, a subsidiary of Eldorado, requires the approval of various routine permits and licenses from a number of government agencies, predominantly under the direction of the Ministry of Environment and Energy (the “Ministry”).

Hellas Gold received approval for its Environmental Impact Study in 2011. Since 2012, the Ministry and other agencies have not entirely fulfilled their permitting and licensing obligations primarily as a result of the lobbying efforts by anti-development interest groups. While Hellas Gold is presently unable to complete its full development plans in Halkidiki as a result of the actions and/or inactions of the Ministry and other agencies regarding the timely issuance of routine permits and licenses, the Company remains committed over the long-term to the projects and its numerous stakeholders within the country.

Olympias

The Olympias plant treated 589,675 tonnes of tailings at a grade of 1.99 grams per tonne during 2015. A total of 16,396 ounces of gold were produced during the year. The Olympias plant ceased treating tailings during the first quarter of 2016.

On March 22, 2016, the Company was granted the required installation permit to begin the next phase (“Phase II”) of Olympias.  During 2015 basic engineering for Phase II was completed, and full implementation began with detailed engineering and procurement of long lead items was well advanced by year end. Underground mine development and refurbishment continued at Olympias during 2015, with underground ore production for Phase II projected to begin before the end of 2016. During 2015, 659 meters of underground access were rehabilitated and 1,901 meters of new development were completed. In addition, approximately 330 meters were advanced on the main Stratoni-Olympias decline, bringing total decline advance project-to-date to 1,950 meters. Capital costs incurred in 2015 were $97 million, consisting of $72 million in construction capital and $25 million in capitalized cost for tailings retreatment.

Skouries

Engineering design work for the processing plant and surface facilities progressed during 2015, with engineering at over 93% complete by year end. During the year a substantial amount of the equipment and various steel structures required to complete construction of the plant and facilities were delivered to the Skouries site, with over 80% of the procurement scope completed by the end of the year. Work continued on construction of the process plant and road access was completed to the base of the tailings dam.

Work on the development of the Skouries underground mine design was advanced during 2015 from scoping level through prefeasibility level. The underground mine design is expected to be completed in 2016. The mine is projected to produce 4.5 million tonnes per year using shaft and ramp access with sub level open stoping along vertical development intervals of 60 meters. The open pit is expected to be used for disposal of mill tailings during the life of the underground operation. The open pit is projected to operate for a period of 8 years to be followed by 22 years of underground mining. During 2015 a total of $112.9 million was spent at Skouries, excluding capitalized exploration and capitalized interest.

On January 11, 2016, the Company announced that construction and development activities at the Skouries project were being suspended due to delays in the issuance of routine permits and licenses by the Greek permitting authorities. Environmental protection works and care and maintenance activities continued to be performed in order to safeguard the environment and the assets of the Company at site at a cost of approximately $1.0 million per month.

Stratoni

Stratoni produced 31% less concentrate than in 2014 mainly due to lower mine output. Mine output was impacted by fewer available underground production faces as well as an extended mine shutdown related to Kassandra mines’ permitting issues. Stratoni reported a loss from mining operations of $12.5 million (2014: gross profit $0.6 million). The loss included a write down of inventory to net realizable value of $3.3 million. In addition to the shortfall in production, the profitability of mining operations was impacted by weak lead and zinc prices. Capital expenditures for the year included upgrades to health, safety and environmental equipment, and upgrades to the water treatment plant.

In 2016, the Company expects to process 220,000 tonnes of ore at grades of 6.2% lead, 10.0% zinc and 163 grams per tonne silver.  Sustaining capital for the year is expected to be $10.0 million.

The Mavres Petres Mine currently has a mine life of approximately three years based on the known proven and probable reserves.  Geological potential exists to expand resources at Mavres Petres and extend mine life, however, in order to delineate additional resources, a mining development and drilling campaign would be required at an estimated cost of $25 million over the next three years, assuming timely issuance of any permits that may be required.

Perama Hill

Project engineering was completed during the year on Perama Hill and the project was placed on care and maintenance pending receipt of the Environmental Impact Assessment approval. In 2015, a total of $1.0 million was spent on the Perama Hill project.

source: eldoradogold.com.,  ellinikoschrysos.gr